Jack London Disitrict Association - Development
This page contains information about current and future development projects planned for the Jack London District. JLDA has been an active participant in reviewing planning applications for these projects and has, wherever possible, provided input that will improve them for the benefit of the community.
We extend an open invitation to all developers to discuss their plans with the board of JLDA and to allow us to assist you in outreach to the community before and during the planning application process.
JLDA also maintains an ongoing dialog with City Staff during construction phases of projects to monitor and communicate issues that may arise such as noise, dust, parking and traffic problems.
Retrofit of the Lake Merritt Channel Bridge on Embarcadero
This CalTrans project is to earthquake retrofit the bridge over Lake Merritt Channel on Embarcadero. The project is expected to start late 2009 and last at least a year. During that time Embarcadero will be completely blocked to traffic in both directions while the bridge is rebuilt. Truck traffic to the Port of Oakland which uses this bridge as an alternate route to 3rd Street (which is a truck route) will be diverted during construction. CalTrans expects to hold a community meeting to discuss the project about 6 months before it starts. JLDA will keep the community informed. Labels: announcements, development
Projects under construction
311 2nd Street - Project name
- 311 Second
- Address
- 311 2nd St
- Developer
- Previously the Olson Company, sold to Mike Reynolds
- Construction company
- City info
- Heather Klein, Major Projects, (510) 238-3659
- Number of Residential Units
- 111
- Retail/commercial space
- Ground floor retail/commercial
- Building height
- 74'
- Building stories
- 8
- Approved
- 1/4/2006
- Start date
- Summer 2007
- Expected Completion
- Late 2008
- Current status
- Under construction - concrete pouring, fourth floor
- Website
- None
- Other notes
- This project was sold to Mike Reynolds (who developed the Aqua Via apartment building) after the original developer, The Olsen Company pulled out.
200 Broadway - Project name
- The Ellington
- Address
- 200/210/228 Broadway
- Developer
- The Enterprise Group (owned by Molasky Pacific Properties)
- Construction company
- Swinerton
- City info
- Heather Klein, Projects 238-3659
- Number of Residential Units
- 134
- Retail/commercial space
- 11,000 sf retail
- Parking spaces
- 222
- Building height
- around 180'
- Building stories
- 18
- Approved
- 01/18/06
- Start date
- August 2006
- Expected Completion
- Mid 2008
- Current status
- Construction started in Winter 2006 and the building has now topped out, the outer skin and windows are being added. The ceremonial ribbon cutting was January 16th with units being occupied this spring
- Documents
- Draft EIR, Final EIR
- Website
- the-ellington.com
- Other notes
- Project entitlements acquired from previous developer. Will be the tallest building in JLD until 444 Embarcadero is built
Site G (Amtrak Parking Lot) - Project name
- Site G
- Address
- Amtrak Parking Lot on 2nd St
- Developer
- Jack London Square Partners
- Construction company
- Pankow
- City info
- -
- Number of Residential Units
- None - 1086 parking spaces
- Retail/commercial space
- At least 20,000 sf of neighborhood serving retail
- Building height
- 87'
- Building stories
- 7 plus roof parking
- Start date
- Site clearing started in December 2007
- Expected Completion
- Winter 2008
- Current status
- First floor walls being built.
- Website
- -
- Other notes
- This project will be staged to complete at the same time as site F1 (Jack London Market) and therefore will start after F1 because it will take less time to build. The design was substantially revised following community input and review meetings organized by JLDA
- Documents
- Perspective, Refinements, Second Street Elevation, East Elevation, Amtrak Elevation, West Elevation, Second Street Details, Platform Details
Site F1 (Jack London Square)   - Project name
- Jack London Market (formerly Harvest Hall)
- Address
- Parking lot next to Heinold's along Embarcadero.
- Developer
- Jack London Square Partners
- Construction company
- -
- City info
- -
- Number of Residential Units
- None
- Retail/commercial space
- -
- Building height
- -
- Building stories
- -
- Start date
- Summer 2007
- Expected Completion
- End of 2008, early 2009
- Current status
- Steel framing almost complete.
- Website
- -
- Other notes
- This is an "Embarcadero Canyon" contributing project. Since approval the amount of office space increased and retail space decreased. There are no confirmed anchor tenants for either space although Miette Bakery from SF is apparently in negotiations for space.
Labels: development
Projects still in planning
367-377 2nd St, 370-380 Embarcadero - Project name
- 370 Embarcadero
- Address
- 367-377 2nd St, 370-380 Embarcadero
- Developer
- 370 Embarcadero LLC (consortium)
- Architect
- Ian Birchall + Associates
- Construction company
- ?
- City info
- Heather Klein, Major Projects, (510) 238-3659
- Number of Residential Units
- 95
- Retail/commercial space
- 5,000 sf of ground floor retail space
- Building height
- 85 feet
- Building stories
- 9
- Approved
- ?
- Start date
- Mid 2008 (estimate)
- Expected Completion
- Late 2009 (estimate)
- Current status
- The project has been approved but is now awaiting resolution of a legal dispute between the developer and the former tenant of the Mingles Bar who insists their lease was wrongfully terminated.
- Website
- N/A
- Other notes
- This is an "Embarcadero Canyon" contributing project - but following comments by JLDA the architect included a 5ft set back above the existing roof line of adjacent properties. The architect also modified the design to including venting for restaurants in the retail spaces, and a small 3,000 sf grocery store on second street.
444 Embarcadero - Project name
- Jack London Square Residential Tower
- Address
- 444 Embarcadero St
- Developer
- Jack London Towers LLC
- Construction company
- -
- City info
- Catherine Payne, Major Projects, (510) 238-6168
- Number of Residential Units
- 257
- Retail/commercial space
- 7,650 sf retail
- Building height
- Up to 310'
- Building stories
- Up to 26
- Expected Start date
- 2009 or later
- Expected Completion
- 2010 or later
- Current status
- Pre-application filed, environmental scoping underway
- Documents
- Initial study and environmental review checklist
- Website
- -
- Other notes
- This is an "Emabarcadero Canyon" contributing project. It may be several years before started, another likely candidate for sale of development rights as the planning application appears to be largely speculative. A hi-tech design concept for the tower was circulated in 2007 that is unlikely to be built.
Broadway-Jackson Freeway Project - Project name
- -
- Address
- 880 Freeway between Adeline and Oak
- Developer
- CalTrans
- Construction company
- -
- City info
- -
- Number of Residential Units
- N/A
- Retail/commercial space
- N/A
- Building height
- N/A
- Building stories
- N/A
- Expected Start date
- 2010 or later
- Expected Completion
- 2013 or later
- Current status
- Initial studies being carried out
- Website
- Information page
- Other notes
- This is a project for 880/980 on and off ramp reconfiguration proposed by the City of Alameda to solve their traffic flow problems in the tube. It would have a major impact on JLD residents due to construction, demolition of buildings adjacent to 880, encroachment of space, loss of views and extra traffic.
880 Freeway widening - Project name
- 880 Freeway widening
- Address
- 880 Freeway between Oak and ?
- Developer
- CalTrans
- Construction company
- N/A
- City info
- -
- Number of Residential Units
- N/A
- Retail/commercial space
- N/A
- Building height
- N/A
- Building stories
- N/A
- Expected Start date
- Next five years
- Expected Completion
- At least two years
- Current status
- Design review
- Website
- -
- Other notes
- This is a major CalTrans project to widen the 880 Freeway south of Oak Street
Jack London Square Redevelopment ProjectsThe Jack London Square Redevelopment Project is a series of sites to be developed between Embarcadero and the Estuary (plus a garage at the current Amtrak surface lot) approved by the City in 2004. There is a minimum project of Site D, Site F1 and 66 Franklin which had to be started in the first five years (recently extended by six months) other projects had to be completed within 20 years before renewal of approvals was required. Site F3 (Jack London Square) - Project name
- F3 - Hotel
- Address
- Site of old Jack London Village, now park next to The Landings
- Developer
- Jack London Square Partners
- Construction company
- -
- City info
- -
- Number of Residential Units
- 200+ hotel rooms
- Retail/commercial space
- Conference space
- Building height
- 175'
- Building stories
- 13
- Expected Start date
- Not before 2009
- Expected Completion
- Not before 2010
- Current status
- Approved
- Website
- -
- Other notes
- JLS Partners has repeatedly claimed, ever since approvals in 2004, that they are negotiating with a major hotel chain about operating the hotel. This would make the start of F3 seem imminent, however nothing ever comes of it and it is hard believe they can sell this as a location as a site for a 4 star hotel until the rest of the development is realized. For this reason ir could be one of the last projects to be built if it is truly to be a 4 star hotel. Considering it is not part of the minimum project that must be built in the first five years then it could mean a start date between 2010 or 2020 - a long time to wait for a hotel room.
Jack London Plaza (Jack London Square) - Project name
- -
- Address
- Community space between Site F1 and 66 Franklin-
- Developer
- Jack London Square Partners
- Construction company
- -
- City info
- -
- Number of Residential Units
- Open space
- Retail/commercial space
- N/A
- Building height
- N/A
- Building stories
- N/A
- Expected Start date
- 2008
- Expected Completion
- 2009
- Current status
- This space will likely get landscape to coincide with the completion of Site F1 (Jack London Market). Therefore we expect to see it started in mid to late 2008.
- Other notes
- Design concepts show the space to be covered and uncovered, provide some parking, and also be home for market stalls.
Site D - Project name
- Site D
- Address
- Foot of Broadway on site of parking lot and former TGIF retail space
- Developer
- Jack London Square Partners
- Construction company
- -
- City info
- -
- Number of Residential Units
- None
- Retail/commercial space
- Office (plus optional movie theater)
- Building height
- N/A
- Building stories
- 7
- Expected Start date
- Not before 2009
- Expected Completion
- Not before late 2010
- Current status
- Approved but likely to change
- Website
- -
- Other notes
- This site was proposed to be an art house movie theater and a major draw to the foot of Broadway. However the decline of the movie business means that no one is building new theaters, least of all next to an existing one. The existing theater also declined to move to the new location. Therefore current plans do not include a movie theater or any retail leaving an office block at the gateway to Jack London Square and foot of Broadway, Oakland's key street. In theory this project should start within five years of approvals i.e. by 2009, however at the moment this seems unlikely. This is an "Embarcadero Canyon" contributing project.
Site F2 - Project name
- Site F2
- Address
- Between The Landings and Site F3 (Harvest Hall)
- Developer
- Jack London Square Partners
- Construction company
- -
- City info
- -
- Number of Residential Units
- None
- Retail/commercial space
- Office space and hotel parking
- Building height
- N/A
- Building stories
- N/A
- Expected Start date
- Not before 2010?
- Expected Completion
- Not before 2012?
- Current status
- No talk of this project starting any time soon (see below).
- Other notes
- As we enter a recession it seems unlikely there will be a need for even more office space at JLS given that 66 Franklin, Site C and Site F1 will all contribute significant office space square footage. It seems likely construction will be delayed until the hotel Site F3 is built which requires the extra parking space provided by F2. As this building provides additional parking for the hotel it seems unlikely it would be built before the hotel, which we believe will be one of the last sites developed. Therefore we don't anticipate this being built before 2010 or much later. This is an "Embarcadero Canyon" contributing project.
Labels: development
Completed projects
288 3rd Street - Project name
- 288 Third
- Address
- 288 3rd St (formerly 300 Harrison St)
- Developer
- Signature Properties
- Architect
- Levy Design Partners
- Construction company
- Signature Properties
- City info
- Joann Pavlinec, Major Projects, (510) 238-6344 Brian Matsumura, Bldg. Permits (510) 238-3882
- Number of Residential Units
- 91
- Retail/commercial space
- Ground floor units are mixed use
- Parking spaces
- 116
- Building height
- ?
- Building stories
- 6
- Approved
- 12/18/2002
- Start date
- February 2005
- Completion date
- First occupancy was December 2006, building finished by Spring 2007
- Website
- 288ThirdStreet.com
- Documents
- Draft EIR figures, Final EIR
- Other notes
- The developers contributed $25,000 towards historic preservation in the Waterfront Warehouse District which it is within the boundaries of.
200 2nd Street - Project name
- 200 Second
- Address
- 200 2nd St (formerly 206 2nd St)
- Developer
- MV Jackson Robinson Brown
- Construction company
- Canon Construction
- City info
- Heather Klein, Major Projects, (510) 238-3659
- Number of Residential Units
- 74
- Retail/commercial space
- 2380 sf of live/work and 1310 sf of retail space
- Parking spaces
- 74
- Building height
- ?
- Building stories
- 6?
- Approved
- 09/03/03
- Start date
- May 2005
- Completion date
- Winter 2006
- Website
- 200Second.com
- Other notes
- -
428 Alice Street - Project name
- 428 Alice
- Address
- 428 Alice St (formerly 426 Alice)
- Developer
- Pulte Homes
- Construction company
- Howard S. Wright
- City info
- Scott Miller, (510) 238-2235
- Number of Residential Units
- 93
- Retail/commercial space
- 9800 sf retail/office
- Parking spaces
- 120
- Building height
- 85'
- Building stories
- 8
- Approved
- July 2002
- Start date
- December 2004
- Completion date
- First occupancy early August 2006, completed by Fall 2006
- Documents
- Draft EIR, Final EIR
- Website
- 428alice.com, 428AliceBlog.com
- Other notes
- This building was constructed on the site of a warehouse building that was demolished. The developers contributed $50,000 towards historic preservation in the Waterfront Warehouse District which it is within the boundaries of.
Aqua Via - Project name
- Aqua Via
- Address
- 125 Second Street
- Developer
- Embarcadero Pacific
- Construction company
- Webcor
- City info
- Heather Klein, Major Projects, (510) 238-3659
- Number of Residential Units
- 100
- Retail/commercial space
- 5190 sf commercial space
- Parking spaces
- 135
- Building height
- ?
- Building stories
- 8
- Approved
- 7/2/03
- Start date
- Winter 2004
- Completion date
- June 2006
- Website
- AquaViaLiving.com
- Other notes
- Rental units - designed for condo conversion
66 Franklin (Jack London Square) - Project name
- 66 Franklin
- Address
- 66 Franklin
- Developer
- Jack London Square Partners
- Construction company
- BBI Construction
- City info
- -
- Number of Residential Units
- None
- Retail/commercial space
- 93,000 sf
- Building height
- -
- Building stories
- 3
- Start date
- 2005
- Completed
- Summer 2006 (except for retail build out)
- Website
- Article on project
- Other notes
- Renovation of existing 1926 Haslett Warehouse building used as office and restaurant space (Old Spaghetti Factory and El Torrito)
Site C (in front of Port building) - Project name
- Site C
- Address
- Water Street between Port building and the Estuary
- Developer
- Jack London Square Partners
- Construction company
- -
- City info
- -
- Number of Residential Units
- None - office and retail
- Retail/commercial space
- At least one floor of retail and one of office
- Building height
- 45'
- Building stories
- 2
- Start date
- Spring 2007
- Completion date
- February 2008
- Current status
- The building is now being leased, several tenants have moved into the upper floor.
- Website
- -
Labels: development
Development Map
We have now created a map of past, current and future development projects in and around the district. You can see it below and it will soon become a permanent feature on our development page. Click on a colored area to read about the project. - Red areas are projects under construction
- Orange are planned but not yet under construction,
- Blue have been through some planning stages but are currently inactive.
- Purple areas are previous developments that have already been built.
Note: the map only shows new construction at the moment therefore building rehabilitations such as New Market Lofts, Tower Lofts, Brickhouse Lofts, and 4th Street Lofts are not included. Please email all corrections, additions and omissions to info@JLDA.org View Larger MapLabels: development, maps
Development Resources
The following is a list of resource that are applicable to all development and construction in the area. For project specific documents and links see the project specific pages. Labels: development, resources
|
|